Publish Time: 2024-04-02

In November 2023, our company undertook the roof renovation door and window project of Foshan Huipai Textile Co., Ltd. This project was designed by our side. Based on the construction site, practical conditions and our many years of construction experience, we provided Party A with practical materials and construction plans at the optimal cost, which was highly recognized by Party A. This project is being constructed on a six-story building with a roof over 30m high, without any safety measures such as external frames. The total project volume is 800㎡, the window system is 3.5m high, and the maximum width of a single window is 13m. It is extremely difficult and safety issues are the top priority. Heavy. Therefore, throughout the entire process, our safety officers were on site at all times to conduct safety supervision. In the end, it took 45 days to achieve safe completion.









×